• support@dumpspool.com
SPECIAL LIMITED TIME DISCOUNT OFFER. USE DISCOUNT CODE TO GET 20% OFF DP2021

PDF Only

$35.00 Free Updates Upto 90 Days

  • C_TSCM42_67 Dumps PDF
  • 106 Questions
  • Updated On April 15, 2024

PDF + Test Engine

$55.00 Free Updates Upto 90 Days

  • C_TSCM42_67 Question Answers
  • 106 Questions
  • Updated On April 15, 2024

Test Engine

$45.00 Free Updates Upto 90 Days

  • C_TSCM42_67 Practice Questions
  • 106 Questions
  • Updated On April 15, 2024
Check Our Free SAP C_TSCM42_67 Online Test Engine Demo.

How to pass SAP C_TSCM42_67 exam with the help of dumps?

DumpsPool provides you the finest quality resources you’ve been looking for to no avail. So, it's due time you stop stressing and get ready for the exam. Our Online Test Engine provides you with the guidance you need to pass the certification exam. We guarantee top-grade results because we know we’ve covered each topic in a precise and understandable manner. Our expert team prepared the latest SAP C_TSCM42_67 Dumps to satisfy your need for training. Plus, they are in two different formats: Dumps PDF and Online Test Engine.

How Do I Know SAP C_TSCM42_67 Dumps are Worth it?

Did we mention our latest C_TSCM42_67 Dumps PDF is also available as Online Test Engine? And that’s just the point where things start to take root. Of all the amazing features you are offered here at DumpsPool, the money-back guarantee has to be the best one. Now that you know you don’t have to worry about the payments. Let us explore all other reasons you would want to buy from us. Other than affordable Real Exam Dumps, you are offered three-month free updates.

You can easily scroll through our large catalog of certification exams. And, pick any exam to start your training. That’s right, DumpsPool isn’t limited to just SAP Exams. We trust our customers need the support of an authentic and reliable resource. So, we made sure there is never any outdated content in our study resources. Our expert team makes sure everything is up to the mark by keeping an eye on every single update. Our main concern and focus are that you understand the real exam format. So, you can pass the exam in an easier way!

IT Students Are Using our SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Dumps Worldwide!

It is a well-established fact that certification exams can’t be conquered without some help from experts. The point of using SAP Certified Application Associate - Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Practice Question Answers is exactly that. You are constantly surrounded by IT experts who’ve been through you are about to and know better. The 24/7 customer service of DumpsPool ensures you are in touch with these experts whenever needed. Our 100% success rate and validity around the world, make us the most trusted resource candidates use. The updated Dumps PDF helps you pass the exam on the first attempt. And, with the money-back guarantee, you feel safe buying from us. You can claim your return on not passing the exam.

How to Get C_TSCM42_67 Real Exam Dumps?

Getting access to the real exam dumps is as easy as pressing a button, literally! There are various resources available online, but the majority of them sell scams or copied content. So, if you are going to attempt the C_TSCM42_67 exam, you need to be sure you are buying the right kind of Dumps. All the Dumps PDF available on DumpsPool are as unique and the latest as they can be. Plus, our Practice Question Answers are tested and approved by professionals. Making it the top authentic resource available on the internet. Our expert has made sure the Online Test Engine is free from outdated & fake content, repeated questions, and false plus indefinite information, etc. We make every penny count, and you leave our platform fully satisfied!

SAP C_TSCM42_67 Sample Question Answers

Question # 1

Which of the following structural elements does a process order have? (Choose three.)

A. Item data
B. Parallel sequences
C. Relationships
D. Phases
E. Characteristic-based process instructions

Question # 2

Which of the following statements best defines SAP ERP?

A. SAP ERP is an application that supports all processes involving direct customer contact throughout the entire customer relationship life cycle.
B. SAP ERP is an application that a company can use to manage its business processes efficiently.
C. SAP ERP is a system in which advanced planning and optimization processes can be mapped.
D. SAP ERP is a system hardware that includes components such as Purchasing, Sales and Distribution, Materials Management, and Production.

Question # 3

Which activity can trigger an automatic availability check for the components of a production order?

A. Material staging
B. Order rescheduling
C. Order release
D. Goods receipt for a missing part

Question # 4

Which of the following statements about the planning functions available in SAP ECC is correct?

A. Master production scheduling (MPS) refers to preferred planning of important materials.
B. Material requirements planning (MRP) includes automatic capacity leveling.
C. Long-term planning (LTP) is a long-term form of forecast planning.
D. In demand management (DM) material shortage situations are identified and corresponding receipt elements are created.

Question # 5

The final assembly of a finished product should only be triggered when a customer order arrives.Which planning strategy for the finished product do you use?

A. Planning with make-to-stock (strategy 10)
B. Planning at the assembly level (strategy 70)
C. Planning without final assembly (strategy 50)
D. Planning with final assembly (strategy 40)

Question # 6

Which of the following are characteristics of ECC master production scheduling (MPS)? (Choose three)

A. MPS items are planned in a standard MRP run.
B. The planning of MPS and non-MPS items is always carried out in one planning run.
C. Non-MPS items can be taken into consideration by an MPS run.
D. MPS items can be defined on plant level.
E. MPS items can be defined on MRP area level.

Question # 7

What is SAP Solution Manager?

A. A transaction in the SAP ECC system
B. A standalone system that communicates with other systems in a system landscape
C. An add-on industry solution
D. A managed system in a system landscape

Question # 8

For which of the following objects can you enter a confirmation? (Choose two)

A. Work Center
B. Production order operation
C. Production order
D. Trigger Point

Question # 9

What do you have to consider regarding consumption? (Choose two)

A. Consumption takes place on the material level between the planned independent requirements and the planned orders.
B. Consumption is restructured with the planning run.
C. Consumption can take place between order reservations and planned independent requirements, depending on the strategy.
D. Consumption parameters (consumption mode and consumption interval) can be set in the material master or in the MRP group.

Question # 10

What can you use to organize material staging for production orders? (Choose three)

A. Material documents
B. Transfer orders
C. KANBAN
D. Pull list
E. Logistics Information System (LIS)

Question # 11

Your customer does not want to manage value-intensive materials in the warehouse. These materials should be procured directly for the production order.Which BOM item category must you set to fulfill this requirement?

A. D (document item)
B. E (external procurement)
C. M (phantom material)
D. N (non-stock item)

Question # 12

What data can be posted directly via the Plant Data Collection (PP-PDC) interface?

A. Goods receipts
B. Maintenance notifications
C. Confirmations
D. Goods issues

Question # 13

When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)

A. General values from work scheduling view in the material master
B. Standard value from operation in task list
C. User-defined field from operation in task list
D. General operation values in task list
E. General item values in bill of materials

Question # 14

With which functions of the process order can you fulfill the requirements of the Good Manufacturing Practices (GMP) standard? (Choose three.)

A. Material identification and reconciliation
B. Availability check
C. Batch record
D. Resource selection
E. Digital signature

Question # 15

What do you have to consider, when you use the ATP (Available To Promise) checks for material? (Choose two)

A. ATP checks can be carried out automatically when releasing a production order.
B. ATP checks are automatically performed during Material Requirements Planning (MRP) runs.
C. ATP checks are used to evaluate the free capacity on a certain work center.
D. ATP checks are mandatory for lead-time scheduling.
E. ATP checks can be adjusted to also consider future requirements and receipts.

Question # 16

You want to create a new material that - is kept in stock- is externally procured- is used as a component in the bills of material for various final products- must not be sold directlyWhich standard SAP material type do you use?

A. NLAG (non-stock material)
B. FERT (finished product)
C. ROH (raw material)
D. HAWA (trading good)

Question # 17

Which of the following statements about the SAP Solution Manager listed is correct?

A. Solution Manager is part of the SAP ECC System.
B. Solution Manager is an add-on industry solution.
C. Solution Manager is a stand-alone system that communicates with other systems in a system landscape.
D. Solution Manager is a satellite system in a system landscape.

Question # 18

What master data do you need for material replenishment using the KANBAN procedure? (Choose two)

A. Production supply area
B. Rate routing
C. Product cost collector
D. Control cycle
E. Production version

Question # 19

Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.How is the resulting firming interval specified in this scenario?

A. By the planning time fence from the material master
B. By the firming mechanism with the longer firming interval
C. By the manual firming date
D. It is predefined in Customizing.

Question # 20

Which of the following are properties of ECC Multi-Site Planning? (Choose two.)

A. Both withdrawal from alternative plant and withdrawal from another plant are defined via special procurement keys.
B. The use of scope of planning (cross-plant total planning) is mandatory for Multi-Site Planning.
C. When using one-step stock transfer posting, transfer stock is created in the receiving plant.
D. When using two-step stock transport order with delivery, the receiving plant is defined as a customer.

Question # 21

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon should be set equally for all materials by default. However, some materials need to have a different planning horizon.Which procedure do you recommend for setting the planning horizon?

A. Set the planning horizon in the MRP groups in Customizing and store deviant entries in the material masters for the corresponding materials.
B. Set the planning horizon in the plant parameters in Customizing and store deviant entries in the material masters for corresponding materials.
C. Set the planning horizon in the MRP groups and assign deviant entries via the plant parameter settings in Customizing.
D. Set the planning horizon in the plant parameters in Customizing and assign deviant entries via the MRP groups for the corresponding materials.